Alternative Project Delivery Methods for Infrastructure: In the Context of Nepal

Authors

  • Yogesh Dhami Technical Director, Mahashakti Engineering and Construction Pvt. Ltd., Kathmandu, Nepal Author

DOI:

https://doi.org/10.32628/IJSRST2512319

Keywords:

Public Policies in Infrastructure Development, Alternative Project Delivery Methods, Public Private Partnership, Effective Infrastructure Development and Economic Growth, Public Infrastructure Projects

Abstract

Among several indicators used to assess the effectiveness of project execution are cost, schedule, and quality. In Nepal, issues such as cost overruns, delays, and substandard quality are ubiquitous in the public infrastructure sector, while public funds are consistently lagging far behind in delivering the basic infrastructure amenities. The main aim of this research is to review the most progressive models for public infrastructure delivery used in the global infrastructure sector and examine their applicability for Nepal. To fulfill the objectives, desk study methodology was employed, which includes an extensive analysis of pertinent literature, public reports, and articles concentrated on project delivery methods and their effectiveness and selection criteria. The study results substantiate the limitations of adopting the traditional Design-Bid-Build model for public infrastructure service delivery and conclude that alternative project delivery methods (PDMs) are likely to be more effective in addressing the predominant issues in Nepal. While this study put forward alternative PDMs as a solution for uplifting the infrastructure sector in Nepal, future research could greatly benefit from investigating other topics to provide more comprehensive solutions. Hence, the paper can be helpful for understanding the present scenario, practices, setbacks, and potential solutions for infrastructure development in the context of Nepal.

Downloads

Download data is not yet available.

References

Gido, J., Clements, J., & Baker, R. (2018). Successful project management (7th ed.). Cengage Learning, Boston, Massachusetts.

World Bank. (1994). World development report 1994: Infrastructure for development. Oxford University Press, Oxford, England. https://doi.org/10.1596/978-0-1952-0992-1

Oxford Economics. (2014). Capital project and infrastructure spending: Outlook to 2025. PricewaterhouseCoopers International Limited. https://www.pwc.com/gx/en/capital-projects-infrastructure/publications/cpi-outlook/assets/cpi-outlook-to-2025.pdf

Kenig, E.M. (2011). Project delivery systems for construction (3rd ed.). Associated General Contractors of America, Arlington, Virginia.

Ministry of Finance. (2024). Budget speech of Fiscal year 2024/25. https://www.mof.gov.np/site/publication-detail/3379

Financial Comptroller General Office. (n.d.). An annual statement of income and expenditure of the Government of Nepal: Financial year (2014/15 – 2023/24). https://www.fcgo.gov.np/reporttypes & https://www.fcgo.gov.np/daily-budgetary-analysis

Government of Nepal. (2007a). Public Procurement Act. https://old.ppmo.gov.np/ppmo.gov.np/image/data/files/acts_and_regulations/2080.pdf

Government of Nepal. (2007b). Public Procurement Regulation. https://old.ppmo.gov.np/ppmo.gov.np/image/data/files/acts_and_regulations/2080.pdf

Fong, C.K., Avetisyan, H.G., & Cui, Q. (2014). Understanding the sustainable outcome of project delivery methods in the built environment. Organizational Technology and Management in Construction: An International Journal, 6(3), 1141–1155. https://doi.org/10.5592/OTMCJ.2014.3.9

Lichtig, W.A. (2010). The integrated agreement for lean project delivery. In M. Kagioglou & P. Tzortzopoulos (Eds.), In book: Improving healthcare through built environment infrastructure (pp. 85–101). Blackwell Publishing Ltd, Hoboken, New Jersey, United States. http://dx.doi.org/10.1002/9781444319675.ch6

Government of Nepal. (2021). Directives on procurement through EPC-2021. https://old.ppmo.gov.np/ppmo.gov.np/image/data/files/acts_and_regulations/2080.pdf

Nepal Electricity Authority. (2024). An annual report: Fiscal year 2023/24. https://www.nea.org.np/annual_report

Republica. (2023, August 26). Editorial view on the China-Nepal industrial park project in Jhapa to progress as Investment Board Nepal expedites PDA process. Republica, Kathmandu. https://myrepublica.nagariknetwork.com/news/china-nepal-industrial-park-project-in-jhapa-to-progress-as-ibn-expedites-pda-process/

Dahal, S. (2017, March 21). Fast track to lost track. The Kathmandu Post, Kathmandu. https://kathmandupost.com/opinion/2017/03/21/fast-track-to-lost-track

List of national pride projects. (n.d.). National Planning Commission. Retrieved October 28, 2024, from https://npc.gov.np/en/page/national_pride_projects

Office of the Auditor General. (2024). 61th Annual report of Auditor General: Fiscal year 2022/23. https://oag.gov.np/menu-category/926/en

Al Khalil, M.I. (2002). Selecting the appropriate project delivery method using AHP. International Journal of Project Management, 20(6), 469–474. http://dx.doi.org/10.1016/S0263-7863(01)00032-1

Nasser, F.M.M., Alawi, N.A., Abaidullah, M., & Yusuf, A. (2023). Emperical analysis of the relationship between project delivery methods on project performance in the Yemen construction industry. American Journal of Economics and Business Innovation, 3(1), 1–8. https://doi.org/10.54536/ajebi.v3i1.2253

Transportation Research Board. (2009). A guidebook for selecting airport capital project delivery methods. Transportation Research Board, Washington, D.C.

Syed Zuber, S.Z., Mohd Nawi, M.N., Abdul Nifa, F.A., & Bahaudin, A.Y. (2018). An overview of project delivery methods in construction industry. International Journal of Supply Chain Management, 7(6), 177–182.

Gransberg, D.D. (2013). Construction manager/general contractor (CMGC) project delivery: A better, faster, smarter way of building transportation infrastructure. TR News, Transportation Research Board, National Academies, 285, 9–15.

American Institute of Architects. (2005). Construction manager at risk state statute compendium.

Construction delivery models. (n.d.). EPCM Holdings. Retrieved December 2, 2024, from https://epcmholdings.com/construction-delivery-models/

EPC and EPCM , Project delivery methods. (2020). MinterEllison. Retrieved December 4, 2024, from https://constructionlawmadeeasy.com/construction-law/chapter-2/epc-and-epcm/

Killough, D. (2024). 6 construction project delivery methods compared. Procore. https://www.procore.com/library/construction-project-delivery-methods

Federal Highway Administration. (n.d.). DBOM, Alternative project delivery defined. U.S. Department of Transportation. https://www.fhwa.dot.gov/ipd/alternative_project_delivery/defined/new_build_facilities/dbom.aspx

Pakkala, P. (2002). Innovative project delivery methods for infrastructure: An international perspective. Finnish Road Enterprise, Helsinki. https://www.tieh.fi/julkaisut/pdf/pakkalae5.pdf

Primer on project delivery (2nd ed.). (2011). American Institute of Architects & Associated General Contractors of America, United States.

Zimmermann, J., & Aljuboori, O. (2013). The challenges of governing public-private partnerships in Iraq infrastructure projects. Proceedings of the Creative Construction Conference, Budapest, Hungary.

The Emerald handbook of public–private partnerships in developing and emerging economies: Perspectives on public policy, entrepreneurship and poverty. (2017). Emerald Publishing Limited, Bingley, United Kingdom.

Zheng, S., & Tiong, R. (2010). First public-private-partnership application in Taiwan’s wastewater treatment sector: Case study of the Nanzih BOT wastewater treatment project. Journal of Construction Engineering and Management, 136(8).

Becker, S.C., Friedinger, C.P., & Sander, P. (2024). Criteria and list of questions for selecting the project delivery method. In M. J. Skibniewski & M. Hajdu (Eds.), Proceedings of the Creative Construction Conference. Budapest University of Technology & Economics and Diamond Congress Ltd., Budapest, Hungary,

Republica. (2024, August 20). Editorial view on the government takes fresh initiatives to launch regular international flights from Pokhara Regional International Airport and Gautam Buddha Regional International Airport. Republica, Kathmandu. https://myrepublica.nagariknetwork.com/news/govt-takes-fresh-initiatives-to-launch-regular-int-l-flights-from-pria-and-gbia/

Mohd Noor, M.I., Mohd Rahim, F.A., & Abd Karim, S.B. (2022). Project delivery method for construction projects: Review of Malaysian public sector practice. Journal of Project Management and Practice, 2(1). https://doi.org/10.22452/jpmp.vol2no1.1